Senum S.A.: Projet Passant Audit Flags 3.4 Milliards FCFA Non-Conformities
Summary
- An independent audit commissioned by Senum S.A. found nearly 3.4 billion FCFA in civil engineering non-conformities for the Projet Passant.
- The 50 billion FCFA project, executed by Lyteca Sénégal and funded by Santander bank, is significantly delayed and currently halted.
- ARCOP identified major irregularities in the project's spontaneous offer, start order, and two addenda, deeming execution "unsatisfactory."
- Senum's communications revealed a 3.5 billion FCFA overvaluation in civil engineering prices and 17 billion FCFA in damages from unexercised contractual rights by previous management.
- Former Senum S.A. Director General Cheikh Bakhoum oversaw the project's execution, which included billing Points of Presence at 93 million FCFA each.
What Happened
The audit points to an estimated 17 billion FCFA in damages resulting from the previous general management's failure to exercise crucial contractual rights.
An independent technical audit commissioned by Senum S.A. has delivered an unfavorable assessment regarding the execution of the Projet Passant, a major initiative carried out between 2019 and 2022. This second Senum audit Projet Passant 3.4 milliards in non-conformities specifically within the civil engineering component. This substantial figure represents 50% of the 6.9 billion FCFA in invoices that were paid after the application of retention, according to information reported by Leral.
The Projet Passant, a significant undertaking valued at 50 billion FCFA, faced scrutiny from its inception, with its contractual framework already a subject of contention. The project is currently experiencing considerable delays and has been brought to a halt, raising serious questions about its overall management and implementation. These findings underscore significant challenges in the oversight and delivery of large-scale public infrastructure projects in Senegal.
Audit Findings and Irregularities
Further investigation into the Projet d’Appui Structurel à la Stratégie d’Aménagement Numérique du Territoire, the formal name for Projet Passant, revealed a series of critical irregularities. A 2023 technical audit, referencing an ARCOP rapport Senum, identified significant issues within the spontaneous offer established between Senum and Liteyca SL. This audit also highlighted problems with the initial start order, dated January 15, 2019, and two subsequent addenda, pointing to fundamental flaws in the project's foundational agreements.
Beyond the initial non-conformités, Senum's own communications indicate a substantial overvaluation of 3.5 billion FCFA in the pricing of civil engineering works. Moreover, the audit points to an estimated 17 billion FCFA in damages resulting from the previous general management's failure to exercise crucial contractual rights. These unexercised rights included the start-up advance, the performance bond, and the application of late penalties, all designed to protect the project's interests. Cheikh Bakhoum, who previously served as the director general of Senum S.A., was at the helm during the project's execution by Lyteca Sénégal.
Regulatory Scrutiny and Financial Context
The regulatory body, ARCOP, formally communicated its findings to Senum on November 29, 2024, concluding that the project's execution was "unsatisfactory" when measured against the stipulated contract clauses. The ARCOP rapport Senum specifically recommended a more thorough examination of unit costs, citing as an example the billing of eight Points of Presence (POP) at 93 million FCFA each, which raised concerns about potential overpricing. These findings highlight systemic issues in Sénégal marchés publics non-conformité.
The Projet Passant was financed through a 50 billion FCFA arrangement with Santander bank, with Lyteca Sénégal responsible for its implementation. The cumulative findings from the independent audit and ARCOP's review, including the Senum S.A. non-conformités and the Liteyca SL Sénégal audit, paint a picture of significant compliance and contractual risks. This situation underscores the critical need for enhanced due diligence and robust contract management in large public sector initiatives to prevent similar findings of overvaluation and unexercised contractual rights, thereby mitigating potential legal and financial repercussions.
Practical Implications
This audit highlights significant compliance and contractual risks in large-scale public projects in Senegal, particularly regarding procurement, contract execution, and financial oversight. Lawyers should advise clients on enhanced due diligence and robust contract management to mitigate exposure to similar non-conformity findings and potential legal repercussions, especially concerning overvaluation and unexercised contractual rights.
Source
Source: Original reporting via Leral
How does this affect you?
Get an AI analysis of this article grounded in your jurisdictions, practice areas, and any policy documents you've uploaded to Wansom.
Finish Reading the Full Story and the Expert Analysis.
Get the latest legal & regulatory intelligence in Senegal
Wansom is AI and can make mistakes.